Thursday 1/26 -

  • Act I scene 7 pages 45 to 55  That is up to “Be Our Guest” Therefore enchanted characters who only appear during the song, will not report Thursday.
  •   Movement rehearsal will remain as scheduled.
Saturday 1/28
  • Costume fitting at the High School as previously scheduled.
  • A wide range of construction projects will be worked on.  Help is needed.  Email me if you can help.
  • Backdrop painting at Sheckler needs the assistance of 5 volunteers.  Volunteers will only be painting in pre-drawn areas of a solid color.  Works will begin with set up of the plastic and drops at 9:00 am. Please email me if you can help.
  • There is also a need for two volunteers with a van or truck to move items from Sheckler to the High School.  Please email me if you can help.
Sunday 1/29
  • Remains as scheduled.  Act II scene 5 from 1:00 to 3:00 and Act II scene 6 from 3:00 to 5:00
  • I would like to add a music rehearsal with the main enchanter characters for “Human Again”  from 2:00 to 3:00.
  • If time permits we will continue work on Act I scene I.
Monday 1/30
  • Act I scene 7
  • When we finish the song if time permits we will review music while I finish blocking the main characters.
That will conclude the blocking of the show except for the 2 scenes so fart that we didn’t finish blocking the first time.
By Monday, February 20th we will be through the show a second time, and expecting to no longer be using scripts.